FAQs
Thank you for attending the Congregational Meeting on April 20th. Click here for answers to your questions.
How are costs being managed?
– Picking the right architect
– Picking the right contractor
– Contractor bidding process
– Overhead & Profit bid
– Transparency of subcontracts (3 bids)
– Willingness to accept penalty
– Value Engineering Process
What are the projected costs?
Construction Costs Subtotal Total |
$4,046,085 $5,113,406 $6,113.406 |
How do we pay for this?
– $2,300,000 already pledged
– Additional already identified in pre-campaign
– Planned capital campaign
– Don’t want any forced assessment
– Don’t want a mortgage
How long will it take?
– Rotunda & Chapel 6 – 7 months
– School & Admin Wing 3 – 4 months
– Social Hall & Sanctuary 3 – 4 months
– Total job 1 year
Avoid holidays
Work around bat/bar mitzvahs & simchas
Can we occupy during construction?
YES, with some careful planning and patience with the inconvenience.